Welcome to our project website

Welcome to the new website and blog home for ShopHouse.  ShopHouse is a LEED Platinum project for our new home.  We have selected tonic design | tonic construction for our Design / Build team.

ShopHouse is a “dream house” for us and here are some specifications for those who are into that sort of thing:

  • LEED for Homes Platinum
  • Energy Star and Healthy House
  • Preliminary HERS rating of 33 (-7 with solar pv installed)
  • Roof insulation:  R50
  • Wall insulation: R26
  • Window insulation value: R9 (more on this later in a blog post)
  • Geothermal heat pumps

With any luck, we’ll be breaking ground in August 2013.  This will be our “homebase” for photo progress, blog posts, links to our partners and everything else for this project.

Recent Posts

Fabulous Finnish Footing forms…

wall-footing-cross-sectionBecause we’re insane (or too dumb to know better  – take your pick…) we decided to take on the job of “manufacturing” the Finnish foam forms for our foundation.

Pay attention to the alliteration – it will come into play later…

Here’s the deal – we have worked so hard to thermally isolate the walls, and build our giant cooler, there was no way we’d just slap them onto a normal concrete footing and let the inner wall be in normal direct contact with both the ground, AND the outer concrete wall.  So – we went about thermally isolating the “inner footing” from the “outer footing”.  Finnfoam was a huge part of that – but so was figuring out how to tie the 2 halves together without traditional metal rebar (a HUGE thermal conductor)

Working with our engineering firm – to make sure all these crazy ideas will actually work… we established the following design:

split-foundation-cross-section

Then – we needed to find the non-conductive rebar – which wasn’t all that difficult (seems to be popular in Canada – gee wonder why…) so we ordered hooks and straights and picked up a pallet.

img_4059

Next, I had to get my head around the fact that footings don’t really attach themselves to the ground and that when you translate the PSI rating of the foam to the PSF spec we had to meet for the compacted earth – and get comfortable with the fact that my ENTIRE FREAKING HOUSE will be sitting on 4″ or FOAM….  Ok – done with that.

We then set out to manufacture the forms.  our design is pretty simple – and we figured that the foam would be standard 8′ (nope – metric) and instead it came in at 8′ 3.5″ or so….  and then the rebar hooks had to be spaced at 12″ increments – we just added a ton on complexity.  Sure we could have cut them all off at 8′, but that actually would have been pretty wasteful.

So – that meant each form was fairly different in where the first hook was placed, that we had upwards of 7 different forms, and that’s before we start talking about how to deal with the corners.

“How hard can it be….?”  Famous. Last. Words.

  1. Finnish footing foam… 487 Replies
  2. Site ready… 1,018 Replies
  3. The Big Dig 1,951 Replies
  4. Cistern Installation 2,529 Replies
  5. Green rating hell. 59,321 Replies
  6. People… 2,346 Replies
  7. LEED for Homes 4, Passive House, Energy Star, DOE Challenge Home, and and and… 3,511 Replies
  8. It’s alive! 2,849 Replies
  9. Alexhouse – Personal 3,462 Replies